Greater Stella Area Development Progress Report

Thursday 6 October 2016

Good progress has been made on the final stages of the Stella development programme since the FPF-1 floating production facility set sail from Poland in August 2016. The FPF-1 was safely towed to the field, moored on location and the dynamic risers and umbilical connecting the subsea infrastructure to the vessel installed as planned. Technip is in the process of concluding the remaining subsea commissioning works. At the same time the FPF-1 offshore commissioning programme is on-going, with preparation of the topsides processing and utility systems for the introduction of hydrocarbons underway. The scheduled completion of these activities remains in line with previous guidance, with first hydrocarbons from the Stella field anticipated in November 2016.

Significant progress was also made during the Quarter on the work programme associated with making the switch from tanker loading to oil pipeline exports for the Greater Stella Area in 2017. The 44 kilometre spurline from the FPF-1 to the Norpipe system was successfully installed as planned in September 2016. The key outstanding activities that now remain to be completed are the manufacture and installation of pipeline export pumps on the FPF-1 and the final subsea connections that need undertaking immediately prior to the switchover.

Related Oil & Gas Projects